Sewerage Feldmannweg

TU Delft continuously works to improve the campus. Part of this is renewing the subterranean infrastructure such as sewerage, cables and pipelines. This will also have to be done along the Feldmannweg. The sewerage is old and tree roots have damaged it, hampering throughput.

Replacing the sewerage moreover entails connecting bodies of water so their levels can be managed more easily. After replacing the sewerage along the Feldmannweg the subterranean infrastructure in the Leeghwaterstraat will also receive a major overhaul so we can optimise soil hydrology in the central and western parts of the campus.

Get updates using the BouwApp.

Themes
DSC00980
vervanging riolering Feldmannweg TU Delft

Facts & figures

  • Street length 300 metres
  • 1,600 metres of new sewerage

Scheduling

  • Start: May  2017
  • Finished: summer 2017